Two more ticket gates, new platform screens and better CCTV are in at Peckham Rye. Two extra doorways come next, and the work ends in late summer 2027.
The queue at the Peckham Rye ticket gates should be shorter from this week. Network Rail has added two ticket gates to the gateline, which it says is 50% more than before.
The old gateline caused a bottleneck. Network Rail says passengers were queuing on both sides of it and up the stairs to get out. The work was announced as finished on 25 September.
What has changed
The first round of work at the station has delivered:
- two extra ticket gates, between the booking hall and the platforms
- new passenger information screens further along platforms 1 and 2
- upgraded CCTV across the station
- more room in the booking hall, where earlier work opened up a section of the station that had been hidden for 30 years
The new screens on platforms 1 and 2 have a purpose beyond information. Network Rail wants passengers to walk further down the platform instead of bunching near the stairs, which crowds both the platform and the front carriages.
Andrew Wood, Network Rail’s senior commercial scheme sponsor, said the changes would make it “quicker and easier to move through the station”. He thanked passengers for their patience during the work.
Why the station needed it
Peckham Rye is served by four train operators. More than 6 million people pass through its booking hall each year. Over a million more change trains there without leaving the station. Network Rail takes those figures from the Office of Rail and Road’s station usage estimates for 2024-25.
That makes it one of south London’s main interchanges. Trains from here reach London Bridge, Victoria and Blackfriars, and the Overground runs east to Canada Water and west to Clapham Junction. Our Dulwich trains to London page compares the journey times from each local station.
Who is paying
The money was announced by Southwark Council in January. The package is worth £5 million:
| Funder | Contribution |
|---|---|
| Department for Transport | almost £4 million |
| Southwark Council and the Railway Heritage Trust | just over £1 million |
What comes next
Work began in May 2026 and the whole programme is due to finish in late summer 2027. Network Rail has set out the order of the remaining work:
- Two more doorways opened into the station building, to make getting in and out easier.
- Narrow sections of platforms 3 and 4 dealt with, to give waiting passengers more space.
- The platform canopies refurbished.
Network Rail has not yet given dates for each phase.
The old canopy is coming back
In June, Network Rail laid foundations for a replica of the original station canopy. The canopy was taken down in 1961. The foundations went in ahead of Southwark Council’s own work on the new public square in front of the station, the Peckham Rye Station Square project.
What this work does not include
The bigger rebuild of Peckham Rye is still unfunded. Network Rail holds planning permission for it and says it “hopes to secure funding” in the future. That scheme would bring:
- new lifts and stairways to every platform
- larger concourse areas
- a new western entrance into Dovedale Court
The current works have been designed so that the larger scheme can still go ahead later. But none of the lifts are part of the work due to finish in 2027.
What it means for you
- Getting out at peak times should be quicker, with six gates where there were four. If you use the station daily, the evening queue up the stairs is the place to notice the difference.
- On platforms 1 and 2, check the new screens further along and use the whole length of the platform. The rear of the train is usually less crowded.
- Expect more work over the next year, including the doorway changes to the station building. Network Rail has not published dates, and we will add them when it does.
- Step-free access is not coming yet. The lifts belong to the larger scheme, which has no funding.
- Rail closures affecting Peckham Rye and Denmark Hill over the coming weeks are on our Dulwich roadworks and travel page. The road changes planned around the station are covered in our story on the Peckham Rye gyratory bus scheme.